Variations

Record changes of scope. An approved variation moves the contract; a pending one waits beside it.

A project’s variations live on its Money tab, under Change orders. A variation changes the contract value only once it is approved:

Current contract value = base contract + approved variations

Pending amounts show beside it, but do not count.

Raise a variation

  1. Choose Add variation.
  2. Give it a Reference (VO-001, for example), the date it was Raised on, and its Amount: negative for a reduction in scope. Zero is refused.
  3. Add a Description, a Note, and an Approval reference if it was approved elsewhere.
  4. Save it as Pending.

Decide

To approve or reject a variation, edit it and set its Status to Approved or Rejected.

Someone other than the person who raised it decides. A company where nobody else can decide approves its own, and that is recorded.

After approval

An approved variation is a record. Only its description, note and approval reference can change, and it cannot be withdrawn. To correct one, raise a new variation for the difference, with the opposite sign.

A variation that is not approved can be withdrawn with Withdraw variation. It stops counting and stays in the record.